We’re pleased to share a progress update on the Northlea School Yard Revitalization Project. Thanks to the continued support of our school community, construction is moving ahead as scheduled.
To date, the existing backstops and all turf have been removed. Asphalt within the designated construction area has also been cleared. Armour stone has been delivered and placed on site, and drainage in the field has been extended in accordance with project drawings. In addition, excavation for a new planting bed has been completed.
The next phase of the project will focus on preparing the site for the installation of the new turf field. Crews will also begin work on the sub-base in preparation for the new asphalt surfacing.
We truly appreciate your continued patience and support as this exciting transformation takes shape. An additional construction update will be shared with families when school resumes in September.